P W Well Services Ltd

Projects

P W Well Services Ltd has worked on numerous projects across the United Kingdom within the conventional oil and gas, gas storage, geothermal, coal bed methane, and other unconventional resource sectors.

We have highlighted some of our recent projects below:

2014

Perenco UK Ltd – Wytch Farm

year 2014
equipment used IDECO SBS EW 60/40 Workover Rig, Power Swivel and Mud Motor
project overview 

Perform workover on the Wareham well; recover existing completion, clean out sump across existing perforations, confirm conditions of casing string, re-perforate the reservoir, run new completion string, install pump and rod string.

Blackland Park Exploration Ltd

year 2014
equipment used IDECO SBS EW 60/40 Workover Rig
project overview 

Pull production and recomplete.

Cuadrilla Resources Ltd

year 2014
equipment used Moor 400 Workover Rig, Cement Batch tank
project overview 

Perform workover on the Preese Hall well for well abandonment. Supported cementing operations in accordance with the Borehole Sites and Operations Regulations 1995. Section milling and cement plugs, batch tank for spacers and pills prior to cement jobs.

I-Gas Energy Ltd

year 2014
equipment used IDECO SBS EW 60/40 Workover Rig
project overview 

Perform workover on the Singleton well. Work activities including cleaning out water injector wells using mud motors adhered to the workover programme. All works carried out under ISSOW and RAMS.

2013

Europa Oil and Gas Plc

year 2013
equipment used Moor 400 Workover Rig
project overview 

Perform workover on the Hykeham well for well abandonment. Set plugs downhole, utilising PWWS cutting casing tools and supporting cementing operations in accordance with Oil & Gas UK guidelines.

Perenco UK Ltd – Wytch Farm

year 2013
equipment used IDECO SBS EW 60/40 Workover Rig
project overview 

Perform workover on the Kimmeridge well; pull existing rod string, undertaken remedial works and inspections, run new completion, pressure testing operations, run new pump and rod string and successfully hand back well to production team.